Pembinaan Loji Rawatan Kumbahan Serantau Cheras Jaya Selangor (M&E)
|
RM 60 Million
(USD 18 Million)
|
Government of Malaysia, Sewerage Services Department
|
Cheras Jaya, Selangor
|
2012
-
on going
|
PROJECT JUSTIFICATION
Construction of Centralised Sewerage Treatment Plant (CSTP) with Sludge Treatment Facilities (1st Module) for 150,000 PE. Consultant is to design the inlet structure for ultimate catchment needs (300,000PE) works
Consultant is to study the use of existing HLT 165 structures such that it could be integrated as part of new CSTP.
|
Bunus STP Project
|
RM550 million
(USD 183 million)
|
JPP
Sewerage
Services
Department
|
Bunus,
Kuala Lumpur
|
2012
-
on going
|
Zone 3A
(Gombak)
This sub-catchment is situated on the north bound of the catchment. This zone comprises of residential areas of Taman Melewar, Gombak Setia, Taman Desa Gombak and Taman Koperasi Polis.
High density residential and commercial area.
Zone 3B
(Bunus)
This sub-catchment comprises the relatively established developments of Wangsa Maju, Wardieburn Camp, Taman Sri Rampai, Taman Setapak, Setiawangsa and Air Panas area.
Mixed development areas consist of residential, commercial, recreational and light industrial area.
Zone 3C
(Ampang-Ulu Kelang
This sub-catchment comprises of residential and light industrial area of Lembah Keramat, Taman Keramat, Taman Melawati, Ukay Perdana and Wangsa Ukay.
High density residential and commercial area.
|
NATIONAL SEWERAGE PROJECT 2
|
RM 983 Million
( USD 298 Million )
|
Ministry of Energy,
Water, and Green Technology, Malaysia
(Kementerian Tenaga, Air
dan Teknologi Hijau,
Malaysia)
|
Pantai Dalam, Kuala Lumpur
|
2011
-
on going
|
The National Sewerage Project 2 consists of the upgrading of existing Pantai Sewage Treatment Plant. This project is known as the Pantai 2 Sewage Treatment Plant Project.
The project involves the decommissioning of the existing aerated lagoons of capacity 560,000 PE by dewatering, desludging and excavation for the construction of a new underground sewage treatment plant with capacity of 1,423,000 PE on a site of 17 ha.
The underground treatment plant will be covered with a 1-2m layer of earth. The reclaimed above ground area will be utilised for the construction of structures including administration center and supporting services such as power plants, biogas generation building, sludge treatment plant, etc and also the construction of sports, recreation and public parks facilities.
Beijing Enterprise Water Group LTD (BEWG) is the Design and Build Contractor for the project. EEC Sdn Bhd is the consultant for Civil and Structural works and lead consultant for the project.
|
KLANG STP LOT130
|
RM120 million
(USD 43million)
|
Ministry of Energy, Green
Technology
And Water,
Sewerage
Services
Department
|
Lot130
Klang
Selatan
Selangor,
Darul
Ehsan
|
2010
-
on going
|
EEC is the design and supervision consultant.
The scope of services includes:
Project evaluation and preliminary design works
Detailed engineering designs which includes civil, structural, process, hydraulics computation and analysis mechanical and electrical designs for sewage treatment plants (STPS) Tender documentation Contract administration and construction supervision works
|