2.8 MW SG. KERLING MINI HYDRO
|
RM 15.20 million
|
Bank Pembangunan Malaysia Berhad (BPMB)
|
Ulu Selangor , Selangor Darul Ehsan
|
2008
|
Scope of works
The works covers all permanent works: mainly the water pipelines, intake weir , power station , mechanical and electrical.
Engineering and Environmental Consultants Sdn Bhd will undertake the role as the Independent Checking Engineer during the construction, testing and commissioning and handing over stages of the said project
We shall act on behalf of the Lender in the reviewing , monitoring and overseeing of the project implementation and management for conformance with established engineering and commercial practices.
|
PRAI POWER STATION - 350MW CCGT
|
RM 1.0 billion
USD 270 million
|
Prai Power
Sdn. Bhd.
|
Prai. Penang
|
1000
|
The services undertaken by EEC for the 350MW CCGT included the following :-
-
Preparation of design concepts and preliminary designs.
-
Worked with financial advisors for negotiation and financial closure.
-
Prepare bid documents.
-
Undertook pre-qualification and tendering.
-
Evaluation and assessment of tenders.
-
Recommendation for award.
-
Undertook PMC supervisory services during construction
-
Evaluate and review EPC Civil Designs.
-
Construction supervision services.
|